Can I update the track_time of person_id 0

Posted on behalf of Graves, Mark. Original posting date 2015-01-22.

Sometimes we have tasks that have yet to be assigned, but we'd like to be able to update those tasks to have correct remaining effort values (using track_time). In my testing, I believe I'm getting a "Bad Request 404" error when I try to update the remaining effort values for an unassigned task. Is this your intent?